Fast-Track or Parallel Design: Acceleration, Risks and the Transformation of Uzbekistan’s Construction Market

18.11.2026

Fast-Track or Parallel Design: Acceleration, Risks and the Transformation of Uzbekistan’s Construction Market

Photo: pexels.com

The architectural and consulting company Archiquad conducted research and spoke with leading professionals in construction, design and urban planning to explore who benefits from this approach, how it can be implemented safely, and what accelerated building construction means for businesses.

What is Fast-Track, how does it work, and how did this approach emerge?

The Fast-Track method is a project delivery format in which design and construction proceed in parallel, with project timelines reduced as much as possible. It emerged in response to economic growth and strong demand for housing.

The shift towards parallel design is a reality of our time. For large-scale projects involving external financing, the Fast-Track format enables developers to move onto the construction site as quickly as possible. Its flexibility allows design solutions to be adapted to the client's requirements in real time, with only minor adjustments needed at the overall project level. Ultimately, this turns speed of delivery into a decisive competitive advantage.

How does the law work in Uzbekistan?

In Uzbekistan, the practice of parallel design is a special procedure under which construction begins simultaneously with the preparation of design documentation. This approach is permitted only in exceptional circumstances: for defence and security needs, disaster recovery, fulfilment of international obligations, or other urgent state objectives. The decision to launch a project is made by the Cabinet of Ministers in coordination with the Presidential Administration. The investor must provide a justification and a set of documents, ranging from an urban-planning assessment to a feasibility study or preliminary project calculations.

In 2020, Shavkat Mirziyoyev signed a resolution authorising construction using the Fast-Track method until the end of 2028.

Fast-Track involves carrying out design and construction simultaneously, followed by the handover of the completed facility. A building or other facility is constructed under an EPC contract (Engineering, Procurement and Construction), which covers:

Engineering — surveys, design and approval procedures;
Procurement — selection and purchase of materials and equipment required for the entire project;
Construction — construction, assembly, installation and commissioning works.

The contractor becomes responsible for delivering the project in accordance with the terms and conditions set out in the contract.

Developers' perspectives

Dmitry Grigoryev, Head of the Construction Department at IBT (PepsiCo), a certified engineer and member of the American Society of Civil Engineers (ASCE), comments:

“An important step has been the introduction of a rating system for design and survey organisations. Thanks to the electronic rating, developers can select reliable design partners. A similar principle applies to construction contractors: companies with a poor track record are filtered out immediately.

The Fast-Track method is not universal and cannot be applied to every project. It is primarily intended for large-scale and strategic developments — government development programmes or major complexes such as Tashkent City, where speed and process transparency are essential. In our estimation, around 5% of projects in the country are delivered using the Fast-Track model, but these account for a share of the largest market players with turnovers exceeding UZS 1 trillion.

The widespread belief that accelerated construction may be linked to cracks in residential buildings is not supported by evidence. Fast-Track is not ‘construction without rules’. It is used only for major projects involving international companies and subject to architectural supervision. Cracks have more often occurred in residential complexes built under standard permits. The causes are different: cutting costs on geological surveys and inadequate building foundations, poor-quality concrete or reinforcement, and insufficient contractor expertise. These problems are associated with attempts to reduce construction time and costs by bypassing mandatory standards.

The construction market is growing today: at the beginning of the year, the sector expanded by 15%, indicating strong investment activity. At the same time, state oversight has become stricter: more rigorous seismic-resistance standards are being introduced, and international practices are being adopted. An escrow account system has been introduced to protect consumer rights: developers must provide financial guarantees, and access to buyers' funds is permitted only when quality standards are met. Environmental requirements are also being tightened. The market has become more mature: transparency, digital reporting and responsibility for the safety of end users are now the priorities.


Long-term returns depend directly on the quality of project management. Effective delivery increases profitability by saving time, while mistakes caused by rushing can wipe out those gains during the operational stage. Saving 20–30% of project time represents a significant financial advantage and makes such projects a priority. At the same time, this approach requires more sophisticated management and the involvement of highly qualified professionals to maintain a balance between speed and quality.”

Andrey Trebunskikh, Head of Product Development at Murad Buildings, comments on the risks and prospects of the Fast-Track format:

“The main advantage of parallel design is the acceleration of financial flows: sales can start earlier, construction and installation works can begin sooner, and the facility can be commissioned faster. However, this speed often comes at the cost of relying on standardised and frequently outdated solutions, as well as excessive safety margins in structural and engineering-system calculations.

The risk of inconsistencies between different design disciplines increases. This leads to errors, additional costs and a decline in quality as early as the construction stage. As a result, time savings can turn into financial and reputational losses if the process is not managed carefully enough.

Against the backdrop of growing competition and increasingly demanding buyers, the Fast-Track model is losing ground in the business and premium segments, where even the slightest decline in quality can be critical for a brand.

It is difficult to establish a direct link between residential building emergencies and accelerated construction. Each case requires a technical assessment: it is important to determine whether the damage affects load-bearing structures, the foundation or only the finishes. The causes can vary widely, from soil conditions and design errors to construction technology violations or work on other buildings in the immediate vicinity.”

Bakhrom Khodjaev, Founder of the architectural company Archiquad, comments on the situation based on his experience:

“International experience confirms that Fast-Track is effective only when all parties involved have a high level of professional expertise and a clear regulatory framework is in place.

In Canada, the method is used to accelerate major projects: parallel design and construction shorten delivery times but require strict quality control. In Malaysia, Fast-Track emerged in response to high demand and tight deadlines. It benefits clients but increases risks for contractors, which is why BIM and digital platforms are being actively adopted there. In Qatar, the method is used in large-scale infrastructure projects, where success depends on transparent communication and government support.

We recognise the advantages of accelerated construction, but we also understand its costs. One of the risks is that rushing can lead to errors, which in turn can increase project costs.

Nevertheless, the Fast-Track method can significantly accelerate project delivery. However, only professional architectural firms with sufficient experience and expertise can manage it successfully. When we took part in accelerated construction projects — including the design of a state university dormitory, a museum and a business centre — our team's international experience helped us successfully integrate and adapt established practices. The use of BIM design also helped reduce the impact of human error and prevent mistakes at the early stages of design.

For a long time, parallel design in Uzbekistan existed in a ‘grey area’: formally, it was permitted only for certain facilities with special authorisation, but in practice it was used much more widely. The state encouraged the construction boom, creating opportunities for developers and accelerating the delivery of major projects. However, these advantages also came with costs: declining quality, safety risks and a lack of transparency in procedures.

The new Presidential decree, which comes into force on 1 July 2026, completely bans parallel design and introduces a phased approval process for documentation. This decision can be seen as a natural stage in the development of the construction industry: first, acceleration to drive growth; now, stricter regulation to ensure quality. Many countries have followed a similar path, and for Uzbekistan this signals a transition towards a more mature regulatory model.

These changes should improve transparency and strengthen trust in the market. In the long term, they represent a step towards ensuring that architecture and construction in the country meet international standards of sustainability and safety.”

Ultimately, the Fast-Track method offers significant advantages in terms of construction speed and economics, but it requires strict regulation and should be used only for strategically important projects. It can be effective only when all participants have a high level of professional expertise, modern technologies such as BIM are used, and a clear regulatory framework is in place.